City of Philadelphia Request for Proposals: Distributed Solar Photovoltaic Project Northeast Philadelphia Airport

The Philadelphia Energy Authority (“PEA”), on behalf of the City of Philadelphia (“City”), requests proposals for electricity and renewable energy credits (“RECs”) to be generated from a 1.5 MWac distributed solar photovoltaic (“PV”) resource at the Northeast Philadelphia Airport (“PNE”), through a long-term power purchase agreement (“PPA” or “Contract”), with a required Placed In Service Date of November 30, 2027. The City department leading this effort is the Department of Aviation (“Department of Aviation” or “DOA”).  If a firm did not respond to the previous Department of Aviation RFPs (September 2019 and March 2021), the firm is still eligible to respond to this Request For Proposals (“RFP”).  RFP issuer wants operational savings on electricity usage at PNE airport buildings, compared to what it would have to pay without a renewable energy project.

Proposals must be received no later than 5 P.M. ET on December 11, 2025. Proposals should be delivered electronically, emailed to PNEsolar@philaenergy.org and Susan.Bailey@phl.org and be no larger than 25MB to ensure delivery.

A general outline of the procurement schedule has been provided below. The Procurement Team will make every effort to hold this schedule. Updates regarding the RFP and its schedule will be posted publicly on the PEA webpage for this RFP opportunity at https://philaenergy.org/public-bids/.

ACTIVITY DATE & TIME
RFP Posted November 7, 2025
RSVP to Non-Mandatory Pre-Proposal Virtual Meeting Deadline

 

November 17, 2025
Email PNEsolar@philaenergy.org and Susan.Bailey@phl.org for meeting link
Non-Mandatory Pre-Proposal Virtual Meeting

 

November 18, 2025, 1:00PM
Meeting link will be emailed when RSVP is sent
Deadline for Submittal of RFP Questions

 

 

November 20, 2025

Submit all questions via email to PNEsolar@philaenergy.org and Susan.Bailey@phl.org

Responses to Questions November 24, 2025
RFP Submission Deadline December 11, 2025 at 5:00 PM EST
Development of Shortlist* December 2025
Developer Virtual Interviews January 2026
Selection of Winner February 2026
Start Contract Negotiations Immediately after Selection of Winner
Contract Review or Approval TBD
Lease Agreement Execution 4th Quarter of 2026
Power Purchase Agreement Execution 4th Quarter of 2026

 